Browse by Year
/ 2010
/ January
/ Friday, January 29, 2010
[Federal Register: January 29, 2010 (Volume 75, Number 19)]
[Notices]
[Page 4791-4793]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr29ja10-39]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
Availability of the Final Environmental Impact Statement (FEIS)
for the Relocation of New River Inlet Ebb Tide Channel Between North
Topsail Beach and Onslow Beach, and the Placement of the Dredged
Material Along the Ocean Shoreline of North Topsail Beach in Onslow
County, NC
AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.
ACTION: Notice of availability.
-----------------------------------------------------------------------
SUMMARY: In accordance with the requirements of the National
Environmental Policy Act (NEPA), the U.S. Army Corps of Engineers (COE)
Wilmington District, Wilmington Regulatory Field Office announces the
availability of a Regulatory Program Final EIS for the North Topsail
Beach Shoreline Protection Project. The applicant, The Town of North
Topsail Beach, is requesting Department of the Army authorization,
pursuant to Section 404 of the Clean Water Act and Section 10 of the
Rivers and Harbor Act, to protect residential homes and town
infrastructures by nourishing approximately 11.1 miles of beachfront
via repositioning the New River Inlet channel, implementing an inlet
management plan to control the positioning of the new inlet channel,
and utilizing an offshore borrow area. The new channel will be
centrally located and the proposal will be to maintain that position,
which essentially will be located perpendicular to the adjacent
shorelines of North Topsail Beach and Onslow Beach. The proposed
sources of the material for the beach nourishment will come from the
repositioning of the inlet and an identified offshore borrow area. The
projected amount of material needed to initially nourish the oceanfront
shoreline is approximately 3.11 million cubic yards. The placement of
beach fill along the Town's shoreline would result in the initial
widening of the beach by 50 to 100 feet. The widened beach would be
maintained through a program of periodic beach nourishment events with
the material extracted from the maintenance of the newly relocated
channel. All work will be accomplished using a hydraulic cutterhead
dredge. The proposed project construction will be conducted in a five
phase approach to correspond with the Town's anticipated annual
generation of funds.
The ocean shoreline of the Town of North Topsail Beach encompasses
approximately 11.1 miles along the northern end of Topsail Island. Of
the 11.1 miles, approximately 7.25-miles of the shoreline in the
project area, with the exception of two small areas, is located within
the Coastal Barrier Resource System (CBRS), which prohibits the
expenditure of Federal funds that would encourage development.
The channel through New River Inlet has been maintained by the COE
for commercial and recreational boating interest for over 55 years. The
COE is authorized to maintain the channel in the inlet to a depth of 6
feet mean low water (mlw) over a width of 90 feet, following the
channel thalweg.
DATES: The Public commenting period on the FEIS will end on March 1,
2010. Written comments must be received at the address listed below no
later than 5 p.m.
ADDRESSES: Copies of comments and questions regarding the FEIS may be
addressed to: U.S. Army Corps of Engineers, Wilmington District,
Regulatory Division, ATTN: File Number 2005-0344, 69 Darlington Avenue,
Wilmington, NC 28403.
FOR FURTHER INFORMATION CONTACT: Questions about the proposed action
and the FEIS can be directed to Mr. Mickey Sugg, Wilmington Regulatory
Field Office, telephone: (910) 251-4811, facsimile (910) 251-4025, or
e-mail at mickey.t.sugg@saw02.usace.army.mil.
SUPPLEMENTARY INFORMATION: The Town of North Topsail Beach, located
along the north-northeast 11.1 miles of Topsail Island in North
Carolina, is proposing to nourish the oceanfront shoreline and
reposition New River Inlet channel as a means to address a severe
erosion problem in order to preserve the Town's tax base, protect its
infrastructure, and maintain its tourist oriented economy. The entire
stretch of the Town's shoreline has experienced a considerable amount
of erosion over the last 20 years due primarily to the impact of
numerous tropical storms and hurricanes during the mid to late 1990's
and due to impacts of the uncontrolled movement of the main ebb channel
in New River Inlet. The Town has stated that the shoreline erosion and
residual effects of the storms have left North Topsail Beach in an
extremely vulnerable position with regard to its ocean front
development and infrastructure. They have estimated that over $250
million in property tax value as well as roads, water and sewer lines,
and other utilities are at risk. The stated overall goals and
objectives of the project are the following: (1) Long-term
stabilization of the oceanfront shoreline located immediately south of
New River Inlet, (2) Provide short-term protection to the 31 imminently
threatened residential structures over the next zero to five years, (3)
Provide long-term protection to Town infrastructure and approximately
1,200 homes, (4) Reduce or mitigate for property damage associated with
shoreline erosion along 11.1 miles of oceanfront shoreline of North
Topsail Beach, (5) Improve recreational opportunities along the Town's
oceanfront shoreline, (6) Ensure material utilized for shore protection
is beach compatible, (7) Maintain the Town's tax base by protecting
existing development and infrastructure on the oceanfront shoreline of
North Topsail Beach, and (8) Balance the needs of the human environment
by minimizing and
[[Page 4792]]
avoiding negative effects to natural resources.
The project is divided into three sections; North, Central, and
South. The North Section starts from the inlet shoulder and runs
approximately 21,000 linear feet along the ocean shoreline. The Central
Section is located both north and south of NC Hwy 210/55 Bridge and is
approximately 16,500 linear feet, while the South Section, which is
outside of the CBRS designation, includes approximately 20,320 linear
feet of shoreline. The Town is proposing to undertake the nourishment
along the 11.1 miles of oceanfront in a five phase approach within a
dredging window between November 16 and March 31 of any year. The first
phase will include the relocation of the inlet channel with the dredged
material being used to nourish approximately 9,000 linear feet of
shoreline in the North Section. Construction timeline for Phase One
will be within the 2010-2011 dredging window. Phase Two would take
place during the 2012-2013 dredging window using the offshore borrow
source, and will nourish approximately 10,120 linear feet in the North
Section. The third phase will include an inlet channel maintenance
event and the use of the offshore borrow material to place material
along approximately 11,500 linear feet within the southern part of the
Central Section. This phase is proposed during the 2014-2015 dredging
window. For Phase Four, offshore material will be used to nourish 6,880
linear feet of shoreline in the north part of the Central Section and
part of the southern tip of the North Section. This construction will
take place in the 2016-2017 dredging window. The final phase of
nourishment will encompass the entire South Section, using the offshore
borrow site and material from an inlet channel maintenance event, and
will be conducted in the 2018-2019 dredging window.
Within the Town's preferred alternative, the relocation of the
inlet channel is a main component in the protection of the North
Section of the project area. The inlet management plan includes the
repositioning the main ocean bar channel to a more southerly alignment
along an approximate 150 degree azimuth and maintaining that position
and alignment approximately every four years. Maintenance events will
be initiated only when established thresholds have been triggered.
These maintenance thresholds include the shoaling of 85% of the new
channel and/or when the thalweg migrates outside of the constructed
500-foot wide corridor. Initial construction of the new channel and
subsequent maintenance events will result in a channel width of 500
feet at -18 foot NAVD depth. The new channel will start within the
inlet gorge and will extend approximately 3,500 linear feet southeast
breaching through the ocean bar. The amount of material to be extracted
during the realignment of the channel is approximately 635,800 cubic
yards. The composite mean grain size of the dredged material is
approximately 0.32mm, compared to the native beach material at 0.23mm.
During additional investigations, it was discovered that an estimated
91,400 cubic yards of the total extracted material is not beach
compatible, consisting of clay and shell. This incompatible material
will be relocated during the dredging operation to an existing dredge
disposal island located at the intersection of the New River and the
Atlantic Intracoastal Waterway, approximately 3.0 miles north of the
project site.
To supplement the initial beach nourishment construction, material
will be dredged from an offshore borrow area. The borrow area is
located directly off of the Central Section, and just southwest of the
NC Highway 210 bridge. Due to the presence of nearby hardbottom areas,
the site is irregularly shaped, with its closest point to the shoreline
at approximately 0.4 miles and its furthest offshore point at 1.6
miles. The site is approximately 482 acres in size and is divided into
16 cuts to separate coarse and fine materials. The division of the
borrow site into coarser and finer materials resulted in the use of the
Point of Intercept Concept or ``perched beached'' for the placement of
material in areas where nearshore hard bottom communities were present.
For nourishment in areas within close proximity to nearshore hard
bottoms, the beach profiles were designed to use coarser material in
order to reduce the fill toe of equilibrium.
The FEIS examines potential impacts to Essential Fish Habitat
(EFH), Threatened and Endangered Species, and includes a comprehensive
mitigation and monitoring plan and the implementation of specific
design measures to minimize potential impacts and to evaluate
unforeseen effects of the projects. Several components in the plan
include incorporating the Point of Intercept design to reduce the
equilibrium beach profile for areas where hardbottom habitats are in
close proximity of the shoreline, incorporation of a monitoring plan to
verify the Point of Intercept design to ensure its effectiveness,
compliance to North Carolina Sediment Criteria Rule for sand
compatibility, winter construction period to occur during lower
biological activities and to avoid nesting turtle season, use of
hydraulic cutterhead dredge and selected pipeline corridors (which will
be GPS) to avoid impacts to hardbottom features, monitoring protocol
during the placement of dredge material onto the beach to comply with
sand compatibility requirements, implementation of a bird and sea
turtle monitoring plan, funding of a research initiative for infaunal
communities conducted by Carteret County Community College,
implementation of an aerial habitat mapping effort for New River Inlet
to survey any short- and long-term effects, and the execution of a
hardbottom monitoring plan which consists of a geophysical survey using
sidescan sonar, underwater investigations that includes habitat
characterization and documentation, and sediment monitoring.
Several alternatives have been identified and evaluated through the
scoping process, and further detailed description of all alternatives
is disclosed in Section 3.0 of the Draft EIS. The applicant's preferred
alternative is to relocate the main ocean bar channel to a southerly
alignment, implement an inlet management plan, nourish approximately
11.1 miles of ocean shoreline, and to construct the work in a five
phase approach.
The COE has initiated consultation with the U.S. Fish and Wildlife
Service under the Endangered Species Act and the Fish and Wildlife
Coordination Act, and with the National Marine Fisheries Service under
the Magnuson-Stevens Act and Endangered Species Act. Additionally, the
EIS assesses the potential water quality impacts pursuant to Section
401 of the Clean Water Act, and is coordinated with the North Carolina
Division of Coastal Management (DCM) to insure the projects consistency
with the Coastal Zone Management Act. The COE has coordinated closely
with DCM in the development of the EIS to ensure the process complies
with State Environmental Policy Act (SEPA) requirements, as well as the
NEPA requirements. The Final EIS has been designed to consolidate both
NEPA and SEPA processes to eliminate duplications.
Copies of the Final EIS will also be available on our regulatory
homepage at http://www.saw.usace.army.mil/WETLANDS/. Locate North
Topsail Beach Shoreline Protection Project under heading ``News from
the Regulatory Program'', and click on ftp.coastalplanning.net. Type
the
[[Page 4793]]
username: ntb and password: ftp4me to pull up the document.
Brenda S. Bowen,
Army Federal Register Liaison Officer.
[FR Doc. 2010-1819 Filed 1-28-10; 8:45 am]
BILLING CODE 3720-58-P
Browse by Year
/ 2010
/ January
/ Friday, January 29, 2010
|
|