Heavenly Valley, L.P.; Notice of Filing
December 30, 2008.
Take notice that on December 22, 2008, Heavenly Valley, L.P.
(Heavenly Valley) filed an application, pursuant to Section 7(c) of the
Natural Gas Act (NGA) and Part 157 of the Commission's Rules and
Regulations, to request certificates of public convenience and
necessity authorizing Heavenly Valley to construct, own, and operate a
natural gas pipeline in Eldorado County, California and Douglas County,
Nevada (Powderbowl Pipeline); and to continue operating an existing
4,500 feet pipeline system at Heavenly Mountain. The application is on
file with the Commission and open for public inspection. This filing is
available for review at the Commission in the Public Reference Room or
may be viewed on the Commission's Web site at http://www.ferc.gov using
the ``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659.
The Powderbowl Pipeline is a 1.86-mile, 4-inch diameter natural gas
pipeline that will begin at Southwest Gas Corporation's existing above-
ground meter station interconnection on the Nevada side and be
terminated at the to-be-constructed Powderbowl Lodge on the California
side. The Powderbowl Pipeline will be constructed entirely in Heavenly
Valley's property. Heavenly Valley also seeks authorization to continue
operating the existing 4,500-feet pipeline which was constructed by
Heavenly Valley's predecessor in 2000 and has been operated by Heavenly
Valley. The 4,500-feet pipeline is also confined in Heavenly Valley's
property. These facilities will provide gas for heating and cooking at
the Powderbowl Lodge. Heavenly Valley plans to complete construction of
the proposed facilities by October 15, 2009.
Any questions regarding the application are to be directed to
Andrew Strain, Vice President of Planning and Government Affairs,
Heavenly Mountain Resort, P. O. Box 2180, Stateline, NV 89449, phone
(775) 586-2313.
Any person wishing to obtain legal status by becoming a party to
the proceedings for this project should, on or before the below listed
comment date, file with the Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426, a motion to intervene in
accordance with the requirements of the Commission's Rules of Practice
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the
NGA (18 CFR 157.10). A person obtaining party status will be placed on
the service list maintained by the Secretary of the Commission and will
receive copies of all documents filed by the applicant and by all other
parties. A party must submit 14 copies of filings made with the
Commission and must mail a copy to the applicant and to every other
party in the proceeding. Only parties to the proceeding can ask for
court review of Commission orders in the proceeding.
Motions to intervene, protests and comments may be filed
electronically via the Internet in lieu of paper, see, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Comment Date: January 21, 2009.
Kimberly D. Bose,
Secretary.
[FR Doc. E8-31429 Filed 1-6-09; 8:45 am]